Experiences with Self‐Consumption Projects
Özgür SARPDAĞ
Business Development Manager
9th of April, Wednesday
Solarpraxis PV Power Plants ‐ Turkey
New Energy
Renewable Energy
Index
1. ELSE Enerji References
2. Self‐Consumption Projects
References
Engineering and Legal Approvals
PROJECT NAME
INVESTOR
LACATION
Işıkyuvar GES
YBT Enerji Yatırım AŞ
Antalya
1.150,00 kWp
Işıkküre GES
YBT Enerji Yatırım AŞ
Antalya
1.150,00 kWp
Ahmet Çelik GES
Ahmet Çelik
Konya
1.150,00 kWp
Besa GES
Besa İnşaat A.Ş
Ankara
1.150,00 kWp
RNT GES‐1
RNT Enerji Üretim AŞ
Niğde
1.000,00 kWp
RNT GES‐2
RNT Enerji Üretim AŞ
Niğde
1.150,00 kWp
Dormak GES
Dormak Danışmanlık AŞ
Ankara
1.150,00 kWp
Taşova GES
Taşova Sulama Birliği
Amasya
1.000,00 kWp
Multielektrik GES
Multielektrik Solar Ltd.
Antalya
13,00 kWp
TOPLAM PROJE KAPASİTESİ:
CAPACITY
8.913,00 kWp
References
Turnkey Projects
PROJECT NAME
INVESTOR
LACATION
Hasçelik GES
Has Çelik ve Halat AŞ
Kayseri
1.150,00 kWp
Beşler Tekstil GES
Beşler Tekstil Sanayi AŞ
Kayseri
1.150,00 kWp
Özkoyuncu Maden. GES
Özkoyuncu Madencilik AŞ Kayseri
1.012,00 kWp
Özkoyuncu Enerji GES
Özkoyuncu Enerji AŞ
Kayseri
1.035,00 kWp
Prokon AŞ GES
Prokon İmalat ve Mon. AŞ Ankara
500,00 kWp
Marka Grup GES
Marka Grup Besi Çift. AŞ
Sivas
500,00 kWp
Dülükbaba GES
Şehitkamil Belediyesi
Gaziantep
40,00 kWp
BriSA Academy GES
Lassa Lastik San.veTic. AŞ
İzmit
22,00 kWp
Kayaşehir 17.Etap GES
Toplu Konut İdaresi Bşk.
İstanbul
62,00 kWp
TOPLAM PROJE KAPASİTESİ:
CAPACITY
5.471,00 kWp
Self-Consumption Projects
Legal Infrastructure
• Unlicenced Electricity Production Regulation provides that
real and legal persons fulfilling certain minimum legal
requirements are exempt from the requirement of
obtaining a license and establishing a company in order to
generate electricity.
• With the Regulation, it is possible to establish a generating
station or power plant, the installed power capacity of
which is limited to a maximum of five hundred kilowatts
based on renewable energy sources
Self-Consumption Projects
Legal Infrastructure
• Unlicenced Electricity Production Regulation
provides that real and legal persons fulfilling certain
minimum legal requirements are exempt from the
requirement of obtaining a license and establishing
a company in order to generate electricity.
• With the Regulation, it is possible to establish a
generating station or power plant, the installed
power capacity of which is limited to a maximum
of five hundred kilowatts based on renewable
energy sources
Self-Consumption Projects
Using Domestic Product
• If the mechanical and/or electro‐mechanical
equipment which are used in power plants are
based on renewable energy sources and which
commenced operation before 31.12.2015, are
manufactured in the country then, the prices set
forth Schedule No.II attached to the law hereby are
added to the prices set forth in the Schedule No.I
for the electric energy given to the transmission or
distribution system after being produced in such
plants, for 5 years from the operation
commencement date of the power plant.
Self-Consumption Projects
Using Domestic Product
Schedule No. II
Type of Facility
C‐ Photovoltaic
solar power
based
production
facility
Domestic Production
Domestic Contribution
US Dolar Cent/kWh
1 – PV panel integration and
solar structural mechanics
production
0, 8
2 – PV modules
1,3
3 – Cells forming the PV Module
3,5
4 – Inverter
0,6
5 – Material focusing the solar light onto the PV Module
0,5
Self-Consumption Projects
Net Metering
Daily Cons. Metering
Daily Prod. Metering
Monthly
Payment
Self-Consumption Projects
Example‐01 / Prokon Project
• Capacity: 500 kWp
• Estimated Production: 700.000 kWh/year
• Consumption of Factory: 1.750.000 kWh/year
• Solar Energy Percentage: %40
• Selling to Grid: %0
Self-Consumption Projects
Example‐01 / Prokon Project
Self-Consumption Projects
Example‐01 / Prokon Project
Self-Consumption Projects
Example‐02 / Marka Grup Project
• Capacity: 500 kWp
• Estimated Production: 750.000 kWh/year
• Consumption of Farm: 350.000 kWh/year
• Solar Energy Percentage: %215
• Selling to Grid: %53
Self-Consumption Projects
Example‐02 / Marka Grup Project
Self-Consumption Projects
Example‐02 / Marka Grup Project
Self-Consumption Projects
Financial Situation
• Capacity: 500 kWp
• Estimated Production: 750.000 kWh/year
• FiT Value:
94.000 USD/year
(gross return‐TEDAS cost added)
• Consum Value: 100.000 USD/year
(electricity price: 0,29 TL/kwh
without VAT)
Thanks for your attention…
Head Office:
Anadolu Bulvarı 994 Sk. No:11/B PK: 06210
Aşağı Yahyalar / Yenimahalle /ANKARA
Tel: +90(312) 394 60 98 Fax: +90(312) 332 33 03
Branch Office:
Saray Mah. Dr. Adnan Büyükdeniz Cad. No:4
Akkom Ofis Park 2. Blok Kat:10 Ümraniye, İstanbul
Tel: +90(216) 250 32 07 Fax: +90(216) 250 32 32
www.elseenerji.com
Download