SEFERİHİSAR-KORMAZ WEPP ( 24 Mw )
Work
: Construction works of 24 Mw installed Power Seferihisar – Korkmaz
WEPP
Location
: İzmir Province, Seferihisar Town, Sığacık Settlement
Employer
: AYEN ENERJİ A.Ş.
Contract Date
: 20.02.2012
Work Completion Date : 02.10.2014
Project Cost
: TL. 6.555.314,00
Scope of the Work
: Road modification in between the Main Road and the Power Plant Entrance
(7000 m in various areas)
Turbine Storage Area Preparation : 4000 m2
Turbine Access Roads : 4920 m
Turbine Foundations and Platforms (Preparation of 12 each turbine platforms
(80.000 m2) and foundation excavation, concrete, formwork, steel works,
back fill)
Cable Conduits
Control Building
Guard House
Turbine and Buildings Wire Fence